No Objection Certificate from BWSSB for Providing Water Supply and UGD facilities with in the BBMP limits
Any owner of the property in the jurisdiction of BBMP area who propose to construct the building for Residential/Commercial purpose or form the Residential Layout.
BWSSB is collecting the following charges at the time of issuing NOC:
1. NOC Charges : On Total Built up Area
I. Residential Apartment/ Commercial/ Educational institutions/ Hospitals: Rs.25/- per square meter.
II. Minimum NOC Charges: Rs.1,50,000/- ( If the NOC charges is less than < Rs.1,50,000/- minimum of Rs.1,50,000/- will be charged)
2. 15% Advance Probable prorata charges collected for total builtup area
I. Residential Buildings: Rs.400/- per square meter of builtup area
II. Commercial Buildings: Rs.600/- per square meter of builtup area (If the proposed building is coming under the core area jurisdiction, then the above said NOC charges and 15 % advance probable prorata charges will be levied to the Total built up area.)
3. Beneficiary Capital Contribution Charges- GBWASP/BCC Charges
I. GBWASP Charges: For the buildings coming under 7 CMCs (Bommanahalli, Mahadevapura, K.R.Puram, Rajarajeshwari Nagar, Dasarahalli, Byatarayanapura, Yelahanka) and 1 TMC (Kengeri) or
II. BCC Charges: For the buildings coming under 110 Villages ( If the proposed building is coming under the 7 CMC & 1 TMC area, then above said NOC charges, 15 % advance probable prorata charges and GBWASP charges will be levied to the Total built up area or If the proposed building is coming under 110 Villages area, then the above said NOC charges, 15 % advance probable prorata charges and BCC charges will be levied to the Total built up area) 4. Charges for Utilization of Treated Water for Construction Purpose
6 months from the Demand note issued date
3 years from the NOC issued date
Prorata Charges are one time charges collected for improvement &strengthening of infrastructure due to increased demand of cauvery water and also for creation of STP’s and strengthing of UGD network for the increased waste water generated in Bangalore.
Beneficiary Capital Contribution Charges towards providing water supply and UGD facilities to 7 CMC & 1 TMC area (GBWASP Charges) and 110 Villages area (BCC Charges)
Core area: Core part of Bangalore i.e 245 Sq.kms
7 CMC & 1 TMC area: The area coming under 7 CMCs Bommanahalli, Mahadevapura, K.R.Puram, Rajarajeshwari Nagar, Dasarahalli, Byatarayanapura, Yelahanka and 1 TMC Kengeri – 330 Sq.kms
110 Villages- Newly added area to BBMP limits: 225 Sq.kms
Through online or by D.D. drawn in favour of Chairman, BWSSB payable at Assistant Controller(Accounts), BWSSB,1st Floor, Cauvery Bhavan, Bangalore-560009.
The difference between the amount collected towards prorata and GBWASP/BCC charges at the time of NOC for the proposed area and actual construction area shall be paid at the time of sanctioning the water supply and sanitary connection.
15 working days